Monday, November 29, 2010

little steps

fascia complete and electrical wiring complete

blocks in place for the water feature

new switchboard

old bathroom (see before pic below) ready for the plumber to finish installing the fittings tomorrow  

laundry still in bits   

new bathroom waiting for the plumber to finish tomorrow

kitchen bits and pieces

kitchen cabinets

old part of the house painting in progress

Sunday, November 21, 2010

Painters tomorrow x



Nearly finished, if the painter turns up and the tiler and the plumber and the sparkie and if the shutters arrive and the missing windows and if the floor sander is on time etc.

Thursday, November 4, 2010

All trades

Everything is moving along now, all trades working on the house. If all goes to plan we will be able to move back in by mid-November - hopefully.

Wednesday, November 3, 2010

Progress is being made...at last


I forgot to take the camera today but we have progress. Floor boards down, stacker doors in, and tiler has started on the bathrooms. Kitchen base cabinets should be installed by the week-end. Concrete was poured today for the pool and it is raining tonight so that will help the concrete from getting heat cracks. Soon we should have a house again and the kids a pool by Xmas. :)



Pool Dug Out